Posted by SCRUMstudy® on January 01, 2023
Categories: Project Delivery SBOK® Guide Scaling Scrum Scrum
Because changes are not allowed during a Sprint, the impact and frequency of expected changes may have an impact on the decision related to the length of the Sprint when it is determined. If project requirements are generally stable and major changes are not expected in the near future, the Length of a Sprint may be extended upto 6 weeks. This provides stability to the Scrum Team members to work on the Prioritized Product Backlog requirements for lengthy periods of time without having to go through the related processes that are conducted for every Sprint.
However, if project requirements are not very well defined or if significant changes are expected in the immediate future, the Length of Sprint is typically set at one to three weeks. This provides stability to the Scrum Team members to work on shorter Sprints and deliver results, which can be evaluated by the Product Owner and business stakeholders at the end of the Sprint. This also provides enough flexibility for them to clarify requirements and make changes to the Prioritized Product Backlog at the end of each Sprint.
To get maximum benefits from a Scrum project, it is always recommended to keep the Sprint Time-boxed to 4 weeks or less, unless there are projects with very stable requirements, where Sprints can extend up to 6 weeks.
However, it is important to note that expected change is not the only factor used to determine the Length of Sprint. Other factors that also need to be considered include:
It is important to note that changing the Length of Sprint should not be decided lightly or periodically (e.g. it is not advisable to have the sprint length as 3 weeks this sprint, 2 weeks the next, 4 weeks for the third sprint etc.) Length of Sprint should preferably be consistent. One of the greatest impacts of changing the Length of Sprint is that it causes a reset on all tracking at the project level. Previous velocities may become useless for forecasting and planning of future Sprints. Without an accurate velocity (which is a primary metric in any scrum project), the Scrum Team cannot be measured for effectiveness or adequately choose the number of User Stories to take on when planning for the next sprint. So, once the Length of Sprint is decided, it should preferably be kept constant over the duration of the project or through multiple Sprint cycles.